ORDERS:
FINAL ORDER AND DECISION
STATEMENT
OF THE CASE
This case is
before me pursuant to a request for a contested case hearing filed by
Petitioners Deborah Keil and Gerard Mallon, challenging the denial of their
dock permit application by Respondent South Carolina Department of Health and
Environmental Control (DHEC or Department), Office of Ocean and Coastal
Resource Management (OCRM). A hearing in this matter was held at the offices of
the Administrative Law Court (ALC or Court) in Columbia, South Carolina on
March 24, 2005.
FINDINGS OF
FACT
Having observed the
witnesses and exhibits presented at the hearing and closely passed upon their
credibility, taking into consideration the burden of persuasion by the parties,
I make the following Findings of Fact by a preponderance of the evidence:
1. Petitioners
are the owners of property located at 35 Rebellion Road, South Windermere
subdivision, Charleston, South Carolina. Their property fronts a marsh which
is in an L-shaped configuration that creates, in effect, a cove. Petitioners’
extended property lines are parallel to Coburg Creek, while some of the other property
owners’ extended property lines along the L-shaped marshfront are perpendicular
to Coburg Creek.
2. Petitioners
first became involved in the dock permitting process when a neighbor, Dr. Harry
Needle, applied for a private, recreational dock to reach Coburg Creek in
1999. Dr. Needle’s extended property lines reach Coburg Creek. Petitioners objected
to the permit on the grounds that the dock would cross a tributary of Coburg
Creek, which they contended was navigable. The Department nevertheless issued
the permit to Dr. Needle and Petitioners subsequently appealed. The Honorable Ray N. Stevens reversed the staff and held that the permit application should be denied because
the dock would cross a navigable creek and would prevent Petitioners' access to
that creek. At the time of Judge Stevens’ decision, Petitioners had not
submitted an application to the Department.
3. On
February 19, 2002, Petitioners applied to DHEC for a dock permit. The permit
application (P/N OCRM-02-087-M) stated that Petitioners were requesting a
204-foot joint use dock to reach a tributary of Coburg Creek. The drawing
showed a walkway beginning from Petitioners' highground property, extending out
for 84 feet, making a 90-degree turn, and extending another 120 feet to reach
the tributary. The drawing also included perforated lines, which illustrated
future walkway connections for which the other property owners could apply.
Petitioners
testified that it is their wish for all of the property owners who front the
marsh to have access to the water via a community dock. What they proposed to
construct is the first leg of the community dock, in hopes that the remaining
property owners on the marsh would be allowed to “tie in” to their walkway.
However, the record reflects that the only individuals whose names were on the
application were those of Petitioners. Even though they represented to the
Court that there were verbal expressions of support, they presented no evidence
of any written commitment or endorsement from the affected property owners; namely,
those whose property fronts the marsh. Moreover, the application did not
provide for access for any other properties along the marshfront.
4. Based
on the description and the drawing, the staff placed the application on public
notice as a private recreational dock and not a community dock. On, July 15,
2002, the dock permit was denied. The staff concluded that Petitioners’
property was not waterfront based on the drawing submitted with their
application. Additionally, the application was denied on the grounds that the
dock, as it was proposed, constituted a single-use dock and would, if
constructed, have a negative impact on the adjacent property owners’ value and
enjoyment. Thereafter, Petitioners requested a contested case hearing before
this Court.
5. I find that though Petitioners intended to obtain
a community dock, the application is in actuality seeking a single-use private
dock. Furthermore, the evidence did not establish that a straight-line
extension from Petitioners’ upland property would reach the navigable
watercourse upon which they seek a dock within 1000' of the marsh critical line.
Their proposed dock would also significantly cross extended property lines
without sufficient evidence of consent by the affected property owners.
CONCLUSIONS OF LAW
Based upon
the foregoing Findings of Fact, I conclude the following as a matter of law:
1. The
Administrative Law Court has subject matter jurisdiction in this proceeding
pursuant to S.C. Code Ann. §§ 1-23-600(B) and 1-23-310 et seq.
(Supp. 2004). Furthermore, S.C. Code Ann. § 48-39-150 (Supp. 2004)
specifically authorizes the Administrative Law Court to hear contested cases
arising under Chapter 39 of Title 48 of the Code.
2. S.C.
Code Ann. §48-39-50 (Supp. 2004) gives DHEC the authority to promulgate
regulations, which carry out the provisions of the Coastal Zone Management
Act. Additionally, OCRM is the division within DHEC charged with implementing
the State’s coastal zone policies and issuing permits for construction within
the critical area.
3. After
Petitioners rested their case, DHEC requested an involuntary non-suit
contending Petitioners had not met their burden in their case in chief. Generally,
in administrative proceedings, the burden of proof rests upon the party who
asserts the affirmative of an issue. Leventis v. South Carolina Dept. of
Health & Env. Control, 340 S.C. 118, 132-33, 530 S.E.2d 643, 651 (Ct.
App. 2000). The burden is to persuade the Court by a preponderance of the
evidence. Nat'l Health Corp. v. S.C. Department of Health and Environmental
Control, 298 S.C. 373, 380 S.E.2d 841 (Ct. App. 1989). The Rules of the Administrative Law Court do not address the procedure for motions to dismiss following the
presentation of a Petitioner's case. However, ALC Rule 68 provides that: “The
South Carolina Rules of Civil Procedure may, where practicable, be applied in
proceedings before the Court to resolve questions not addressed by these rules.”
Rule 41(b), SCRCP, provides that: “After the plaintiff in an action tried by
the court without a jury has completed the presentation of his evidence, the
defendant. . . may move for a dismissal on the ground that upon the facts and
the law the plaintiff has shown no right to relief.” Furthermore, “Rule 41(b)
allows the judge as fact finder to weigh the evidence and determine the facts.”
Waterpointe I Property Owner's Ass'n, Inc. v. Paragon, Inc., 342 S.C.
454, 458, 536 S.E.2d 878, 880 (Ct. App. 2000). I find that application of Rule
41(b), SCRCP, is proper to this case. Therefore, after Petitioner(s) rest its
case, the ALC as the trier of facts upon a motion for involuntary non-suit may
determine the facts and render judgment against the Petitioner. Accordingly, Petitioners
had the burden to prove that the decision to deny the dock permit was improper,
or in other words, that they are entitled to the dock they requested in their
application.
4. Petitioners
contend that Judge Steven’s decision on December 11, 2000, should control the
decision in this case, under the principle of issue preclusion, or collateral
estoppel. In fact, they based their entire case upon this argument. I
respectfully disagree. “Under the doctrine of collateral estoppel, once a
final judgment on the merits has been reached in a prior claim, relitigation of
those issues actually and necessarily litigated and determined in the first
suit is precluded as to the parties and their privies in any subsequent action
based upon a different claim.” Richburg v. Baughman, 290 S.C. 431, 434,
351 S.E.2d 164, 166 (1986); see also Carman v. South Carolina Alcoholic Beverage Control Comm'n, 317 S.C. 1, 451 S.E.2d 383 (1994)
(applying collateral estoppel in administrative proceedings). The issue before
Judge Stevens was whether the law permitted Dr. Needle to receive a dock
permit. However, the issue of whether Mr. Mallon and Dr. Keil were entitled to
a dock was not litigated before him, much less whether Petitioners were
entitled to the dock that they are seeking in this case. Therefore, Judge
Stevens’ decision does not preclude the litigation of the issues before me.
5. In
the case at hand, it is clear that Petitioners’ goal is to acquire a community
dock so that all of the property owners along the marsh can have access to the
water.
Their hope is that the other property owners would ultimately "tie in"
to their part of the structure. Obviously, an individual(s) cannot seek a
permit on behalf of another person without their permission. This principle is
reflected in OCRM's regulations. For instance, S.C. Code Ann. Regs. 30-2(B)(4)
(Supp. 2004) requires that a permit applicant shall ordinarily be required to
submit: “A certified copy of the deed, lease or other instrument under which the
applicant claims title, possession or permission from the owner of the property
to carry out the proposal.” Although Petitioners’ aspiration of achieving
access for all of the property owners on the marsh is admirable, they did not
submit sufficient evidence to show that the other property owners consent to
this particular dock, or that they have the authority to speak for or act on
behalf of those property owners.
Petitioners’ permit
also fails if viewed as an application for single-use private dock. 23A S.C.
Code Ann. Regs. 30-12 (A)(2)(o)(i)(b) (Supp. 2004)
provides that “[t]o be eligible for a single family dock, a lot must have:
* * *
(b) 75 feet between its extended property lines at the
location in the waterbody of the proposed dock.
23A S.C. Code
Ann. Regs. 30-1 (D)(52) (Supp. 2004) further provides that:
For purposes of these regulations,
waterfront property will generally be defined as upland sites where a
straight-line extension of both, generally shore perpendicular, upland property
lines reaches a navigable watercourse within 1000' of the marsh critical line.
Waterfront property may also be identified via an approved dock master plan
where designated corridors differing from upland property line extensions are
delineated.
Here, the evidence failed to establish that a straight-line extension from
Petitioners’ upland property would reach the navigable watercourse upon which
they seek a dock within 1000' of the marsh critical line. Consequently, since Petitioners’
do not own waterfront property, for purposes of this case, they are not
entitled to a single-use private dock.
Therefore, I conclude that Petitioners did not establish that
they are entitled to the permit proposed in the application. This is not to
say, however, that Petitioners could not re-apply, or that the Department could
not permit a community dock in this area. In other words, the denial of this
application does not preclude Petitioners, or any future owners, from seeking a
permit for a structure that is inclusive of all of the property owners in this
vicinity.
ORDER
Therefore, based on the foregoing Findings of Fact
and Conclusions of Law, it is hereby:
ORDERED that an involuntary non-suit is
granted and, accordingly, permit application number OCRM-02-087-M is denied.
AND IT IS SO ORDERED.
___________________________________
Ralph
King Anderson, III
Administrative
Law Judge
June 23, 2005
Columbia, South Carolina |