ORDERS:
FINAL ORDER AND DECISION
I. Introduction
On January 14, 2004, T&T Disposal, LLC (T&T) obtained from the South Carolina Department
of Health and Environmental Control (DHEC) a construction, demolition, and land-clearing
debris landfill permit. Oakwood Landfill, Inc. (Oakwood) and Hickory Hill Landfill (Hickory
Hill) challenged DHEC’s decision and brought the instant contested case. Jurisdiction vests in
the ALC under S.C. Code Ann. Sec. 1-23-100, et seq., Sec. 44-96-10, et. seq., and S.C. Code
Regs. 61-107.
II. Issues
The issues here stem from S.C. Code Ann. Sec. 44-96-290(F). That section in pertinent part
states the following:
No permit to construct a new solid waste management facility . . . within a county
. . . may be issued by the department unless the proposed facility . . . is [1]
consistent with local zoning, land use, and other applicable ordinances, if any;
[and 2] the proposed facility or expansion is consistent with the local or regional
solid waste management plan . . .;
Oakwood and Hickory Hill first assert that the permit should be either denied outright or
remanded to DHEC for further review since DHEC did not make an independent "consistency"
examination as required by S.C. Code Ann. Sec. 44-96-290(F). Instead, Oakwood and Hickory
Hill assert DHEC improperly delegated the consistency determination to Jasper County.
Second, Oakwood and Hickory Hill argue that even if no improper delegation occurred, the
permit must still be denied since the evidence establishes that the consistency requirements were
not met in two respects. A lack of consistency exists with Jasper County's zoning, land use, and
other applicable ordinances, and a lack of consistency exists with the regional solid waste
management plan.
Finally, Oakwood and Hickory Hill further argue that even if no improper delegation occurred
and even if no consistency problems exist, the permit must be "reformed" by deleting a final
disposal capacity of approximately 2.2 million cubic yards and inserting a disposal capacity of
2.2 million cubic feet.
III. Analysis
Based on the preponderance of the evidence, the following findings of fact are entered:
A. Findings of Fact
In 2002, T&T submitted to DHEC an application for a construction, demolition, and land-clearing debris landfill permit. In reviewing that application, a major factor for DHEC was
determining whether granting the permit would be consistent with the applicable solid waste
management plan.
For consistency purposes, DHEC looked to the 1994 Low County Regional Solid Waste
Management Plan (LC Plan). That plan had been filed with DHEC by the Lowcountry Council
of Governments (LCOG). The plan covered and was "endorsed" by the counties of the region
including Beaufort, Colleton, and Jasper with those endorsements memorialized by letters from
each of the respective governing bodies. The LC Plan was submitted by the LCOG to DHEC as
the regional solid waste plan for the low country counties. As to Jasper County in particular,
Jasper County participated on a local and regional level in the development of the plan, voted to
approve it at a meeting of County Council, and endorsed it by letter to DHEC in February of
1994.
The 1994 LC Plan has not been amended by LCOG since its adoption. However, at the time of
DHEC's review, DHEC had before it a December 2002 draft plan submitted by LCOG which
would replace the 1994 LC Plan. But, since the draft plan had not been approved by the regional
counties, the draft plan played no role in DHEC's consistency review.
While not part of DHEC's review, LCOG on the other hand had begun giving the draft plan
consideration for planning purposes. For example, LCOG notified DHEC by letter dated April
19, 2002, that since a draft plan was in progress it was advisable for DHEC not to issue any
permits in Jasper County. However, on May 29, 2002, LCOG clarified that position by
explaining to DHEC that Jasper County did not object to DHEC issuing a permit to T&T before
the completion of the new plan.
Notwithstanding the fact that Jasper County did not object to the landfill permit, an additional
hurdle for consistency purposes was presented by the LC Plan since it states that for the next
twenty years there is no apparent need to construct additional landfill facilities in the region
covered by the plan. Contrary to the plan, however, Jasper County Council on October 20, 1997,
noted the following in the minutes of its County Council meeting:
Our population is expected to boom over the next several years and another
landfill will probably be needed. Councilman Sneed motioned to allow Mr. Moss
to write a letter stating that the landfill is not inconsistent with the county's solid
waste management plan. Councilman McKenzie seconded the motion. The
motion was carried by all members voting in favor.
The "landfill" referred to in the minutes is the T&T landfill which is at issue in this case.
Consistent with the minutes of October 20, 1997, the requested letter from Jasper County was
subsequently written to DHEC on October 29, 1997. Further, similar letters confirming Jasper
County's favorable position on consistency with the landfill were written to DHEC on September
27, 2000, May 7, 2002, and December 16, 2003.
DHEC considered the letters to be amendments to Jasper County's portion of the LC Plan and
“penciled in” the changes. See Exhibit 5, p. 46. In fact, DHEC had previously considered the
LC Plan as having been amended April 2, 2001 when it allowed an expansion of the Oakwood
facility. Ib. Such letters to DHEC from other entities throughout the State have not been an
uncommon occurrence. When received, DHEC's practice has been to handwrite the change into
the applicable plan at a spot in the plan most reasonable from DHEC’s viewpoint. See Exhibit 5,
p. 46. The practice has been to treat the letters as amendments to the various solid waste plans
whether the letters were submitted by counties operating under regional plans or submitted by
counties operating under separate plans.
In addition to the consistency letters, DHEC had before it minutes from the Jasper County
Council meetings in which Council voted favorably on the matter. The minutes of those
meetings demonstrate that public notice of the meeting was given within Jasper County and that
pubic participation was invited.
In making the consistency determination, DHEC recognized that zoning considerations were
relevant. DHEC asked T&T to supply a letter of compliance with Jasper County's zoning
requirements and did not declare the application administratively complete until T&T complied.
In addition, DHEC had before it a July 24, 2002 letter from the Director of Planning and
Building Services for Jasper County addressing the zoning in Jasper County. Further, DHEC
had before it the applicable ordinance from which DHEC concluded that the "RD" status
imposed by the ordinance allowed a landfill activity like that sought by T&T.
DHEC also came to recognize that T&T had not obtained final permission from Jasper County
as to all land use requirements. Rather, T&T had received only "conceptual approval."
However, Jasper County ordinances prohibited the granting of final approval until DHEC issued
a landfill permit. Given such a condition, DHEC examined the applicable county requirements
and determined that T&T would be able to meet the land use requirements after receiving the
requested landfill permit.
By August 15, 2002, DHEC had determined the application was administratively complete.
Then, after final review, DHEC issued the requested permit on January 14, 2004.
B. Conclusions of Law
Based on the foregoing Findings of Fact, the following Conclusions of Law are entered:
Under the South Carolina Solid Waste Policy and Management Act (SWPMA) "[n]o person
shall operate a solid waste management facility without a permit from the department [DHEC]."
S.C. Code of Laws Ann. Sec. 44-96-290(A) (1976 Code). To comply with the permitting
requirement, T&T filed with and obtained from DHEC a permit to operate a solid waste
management facility in the form of a construction and demolition/land clearing debris landfill in
Jasper County. Oakwood and Hickory Hill believe the permit should not have been granted.
1. Delegation of Consistency Requirements
Oakwood and Hickory Hill argue that the permit should be either denied or the matter remanded
to DHEC for further review since DHEC failed to make an independent "consistency"
examination as required by S.C. Code Ann. Sec. 44-96-290(F). More specifically, Oakwood and
Hickory Hill argue that DHEC delegated to Jasper County the authority to determine consistency
and that such an act is an error of law.
It is first important to note what this case is not. This case is not one in which the agency asserts
a statutory right to delegate its authority. See e.g. Edisto Aquaculture Corp. v. South Carolina
Wildlife and Marine Resources Dept., 311 S.C. 37, 426 S.E.2d 753 (1993) (agency had the right
to delegate since the General Assembly expressed its intent that the two "agencies shall
coordinate their respective efforts."). While coordination is indeed involved in this case, DHEC
correctly chooses not to assert a right to delegate consistency determinations to Jasper County
since our Supreme Court has found that such delegation is improper. Southeast Resource
Recovery, Inc. v. South Carolina Dept. of Health and Environmental Control, 358 S.C. 402,
595 S.E.2d 468 (2004) ("DHEC, not the county, is charged with ensuring such facilities meet
the [consistency] requirements for permitting [construction of a new solid waste management
facility]." Rather, the issue here, simply put, is one of asking what did DHEC do B delegate or
investigate. Oakwood and Hickory Hill claim the former; DHEC and T&T claim the latter.
In the end analysis, for Oakwood and Hickory Hill to establish that DHEC delegated away its
consistency power, proof must exist that DHEC yielded its final decision-making authority to
another. See Riverbend Farms v. Madigan, 958 F.2d 1479, 1488 (9th Cir.), cert. denied, 506
U.S. 999, 113 S.Ct. 598, 121 L.Ed.2d 535 (1992) (the ultimate test of the validity of an agency's
delegation of responsibility is whether the delegating agency retains final decision-making
authority). Proof that DHEC utilized others (be they the applicant or Jasper county) as aids or
sources of information does not establish that DHEC delegated away its final decision-making
authority over consistency. 2 Am.Jur.2d Administrative Law Sec. 224 at 54-55 (1962) ("[T]he
law does not preclude practicable administrative procedure in obtaining the aid of assistants in
the department, apparently to any extent so long as the agency does not abdicate its power and
responsibility and preserves for itself the right to make the final decision."). Indeed, obtaining
information and assistance from county officials is not persuasive evidence of improper
delegation since seeking such is entirely consistent with the cooperation and coordination goals
and findings identified by the General Assembly in SWPMA. See S.C. Code Ann. Sec. 44-96-20(A)(13) and (14) (where the General Assembly finds that "(13) [a] coordinated statewide solid
waste management program is needed . . . [and] (14) [t]he statewide solid waste management
program should be implemented through the preparation of a state solid waste management plan
and through the preparation by local governments of solid waste management plans consistent
with the state plan and with this chapter."); S.C. Code Ann. Sec. 44-96-20(B)(2) (there the
General Assembly explains that one of the purposes of SWPMA is to "(2) establish and maintain
a cooperative state program for providing planning assistance, technical assistance, and financial
assistance to local governments for solid waste management.").
Here, the evidence establishes that DHEC did not delegate away its final decision-making
authority over the consistency determinations for zoning and land use requirements or over the
consistency determination with the local or regional solid waste management plan.
a. Zoning and Land Use Requirements
DHEC made its own determination on local zoning and land use requirements. For example,
instead of yielding that authority to Jasper County for a zoning determination, DHEC looked to
T&T. A checklist used by DHEC asked if T&T had supplied a letter of compliance with Jasper
County's zoning requirements. When such evidence was not included in the initial filing in
2002, DHEC did not declare the application administratively complete until T&T complied.
Certainly, the predominant support for T&T's effort to establish compliance with zoning and
land use requirements came from T&T's supplying of a July 24, 2002 letter from Harold Jones,
the Director of Planning and Building Services for Jasper County. However, that letter was not
all that DHEC considered. DHEC's decision also relied upon its own reading of the zoning
ordinance involved. In fact, DHEC had before it the applicable ordinance and concluded that the
"RD" status imposed by the ordinance allowed a landfill activity like that sought by T&T.
As to building development requirements in Jasper County, again, DHEC did not delegate its
decision making authority to the county. On the contrary, the testimony establishes that DHEC
was not initially on notice from T&T's application that any requirement beyond zoning was a
factor in Jasper County. Thus, the argument is not persuasive which asserts that DHEC
transferred final decision making authority over factors that DHEC did not know existed. Being
uninformed is not the same as affirmatively delegating authority to a third party.
Moreover, the testimony establishes that DHEC often receives applications for which not all
applicable permits have been received from the local authorities. In those instances, the practice
of DHEC is to independently determine if the applicant will be able to meet the county
requirements.
Consistent with the instant case, the testimony establishes that T&T had not yet obtained all of
the final permission from Jasper County officials since the county established that T&T had not
moved from "conceptual approval" to "preliminary approval" in the land use criteria. However,
the evidence establishes that such movement could not take place until DHEC issued a landfill
permit. Thus, virtually by default, DHEC was required to independently decide if T&T could
meet the local requirements for consistency purposes. DHEC made such a determination and
issued the permit. Accordingly, considering the factors here, DHEC did not delegate away its
final decision-making authority over the consistency determinations for zoning and land use
requirements.
b. Regional Solid Waste Management Plan
The lack of delegation of final decision making authority as to the regional solid waste
management plan is plain in this record. Here, DHEC examined a number of factors and
exercised discretionary judgment on the consistency issue. For example, DHEC reviewed no
less than four letters of consistency from and to various individuals related to the T&T landfill
project, examined at least one set of Jasper County Council minutes that stated that the Council
voted to approve the landfill, considered at least one set of minutes that stated that the Council
voted to allow the county administrator to write a letter stating that the proposed landfill was not
inconsistent with the LC Plan, and reviewed at least one letter from Jasper County's Council to
DHEC stating that a majority voted to approve the landfill. These actions all involve
investigation and discretion. None were taken at face value but instead were factors for
consideration. Such actions by DHEC are not indicative of a delegation of final decision making
authority to Jasper County. Accordingly, no improper delegation occurred here.
2. Meeting Consistency Requirements
Oakwood and Hickory Hill argue that even if no improper delegation occurred, the permit must
still be denied since the evidence establishes that the consistency requirements have not been
met. The argument is that the landfill is not consistent with Jasper County's zoning and local
land use ordinances. Second, the landfill is not consistent with the regional solid waste
management plan.
a. Zoning and Local Land Use Ordinances
Here, the evidence establishes that both at the time of T&T's filing of its application and at the
date of the issuance of the permit by DHEC, T&T had not yet obtained all of the final permission
from Jasper County in reference to local ordinances. For example, T&T's plans had not moved
from the Planning Commission's "conceptual approval" (which had been granted) to the next
stage of "preliminary approval" (which had yet been achieved).
However, the lack of such permission is not a basis for finding a lack of consistency. On the
contrary, final approval of T&T's plans could not be secured from Jasper County since final
approval was simply not available. Jasper County's ordinances prohibit final approval until
DHEC has issued the landfill permit. Thus, without a DHEC landfill permit, no requirement
existed for final approval from Jasper County. Therefore, the controlling issue for consistency
with local ordinances becomes deciding whether any plain impediments existed at the time of
the permit application that suggested T&T would be unable to obtain the needed approval from
Jasper County.
No such impediments have been established here. Rather, the testimony shows that Jasper
County officials had no reason then and have no reason now to believe that T&T will not meet
the county ordinances for land use and building development purposes. For example, in a letter
of July 24, 2002, Harold Jones, the Director of Planning and Building Services for Jasper
County, stated he saw no problem with the zoning for the proposed facility. In addition, the
testimony at trial from Mr. Jones confirmed that after receiving a DHEC landfill permit, Jasper
County believed that "[n]othing other than an application" from T&T was needed to meet all
applicable Jasper County ordinances. Accordingly, no lack of consistency exists with Jasper
County's zoning and local land use ordinances.
b. Regional Solid Waste Management Plan
Consistency with the local waste management plan begins with the LC Plan prepared by LCOG
in 1994. That plan resulted from the requirements of SWPMA directing that "the governing
bodies of the counties in a region, if two or more counties intend to submit a regional plan, in
cooperation with the local governments located in the county or region, shall prepare a solid
waste management plan for the area within that county or region." S.C. Code Ann. Sec. 44-96-80(A). Thereafter, the "region shall submit its solid waste management plan to the department
[DHEC] for review [which] . . . shall have one hundred eighty days from the date on which a
plan is submitted to review the plan and provide comments to the submitting entity [and a]t the
end of the one hundred eighty-day review period, the county or region shall begin
implementation of its solid waste management plan." S.C. Code Ann. Sec. 44-96-80(B). Here,
the LCOG submitted the LC Plan to DHEC. The LC Plan was accepted by DHEC, and
implementation in the region began.
As an accepted plan by DHEC, the regional plan properly complies with the statutory mandate
that the plan contain a projection of the need for new solid waste facilities for the region for the
next twenty years. See S.C. Code Ann. Sec. 44-96-80(A)(3). Addressing that mandate, the LC
Plan states the following:
Based on the amount of disposal capacity available in and around the Lowcountry
there is no apparent need to construct new domestic or inert landfill facilities in
the next 20 years.
LC Plan p. 48.
Accordingly, given the plan's clear statement of no apparent need for a new landfill for the next
20 years, the evidence must establish how adding a new landfill in Jasper County is consistent
with the LC Plan. Here, the evidence of consistency is simply not persuasive.
For example, DHEC seeks to find the T&T landfill meets the consistency requirement since
DHEC received information from Jasper County asserting that growth was expected to a degree
warranting another landfill. However, such information does not establish consistency. On the
contrary, the information is entitled to little weigh since the assertion is not supported by
underlying data. Jasper County does not adequately identify the specific projected growth area,
does not establish when the growth will occur, does not state how long it will continue, and does
not establish at what rate the growth will progress. In short, the county's conclusory position is
an insufficient basis for establishing consistency with the existing regional plan.
But, more fundamentally, in light of the plan's position that no apparent need exists for any
landfills for the next 20 years, DHEC and T&T recognize the apparent inconsistency between
the LC Plan and the desire to add a landfill. Thus, they argue that the inconsistency disappears if
the LC Plan has been amended to approve adding a landfill in Jasper County. I find no such
amendment exists.
Here, the lack of any amendment to the LC Plan is supported by the testimony of the executive
director of LCOG. His testimony establishes that the LCOG made no amendments to the plan.
Further, he testified that a new regional plan is in the draft stage but has not been adopted by the
regional counties. Thus, the evidence establishes that the 1994 plan has not been amended from
its 1994 adoption.
The testimony of the executive director of LCOG is supported by the amendment process
established by SWPMA. SWPMA provides that after the regional plan is filed, the region must
submit an annual progress report which "must contain, at a minimum, . . . : (1) any revisions to
the solid waste management plan previously submitted . . ." S.C. Code Ann Sec. 44-96-80(F)(1).
In this case, no revisions of the 1994 LC Plan have been made. On the contrary, only two letters
from LCOG (the entity submitting the LC Plan) have been submitted to DHEC and neither
amends the LC Plan.
The first letter of April 19, 2002 explains that since the LCOG will be completing a new plan in
the near future "it would be advisable at this time to issue no new certificates of need or other
permits in Jasper County." Obviously, such a statement does not amend the plan to add the T&T
landfill.
Similarly, a second letter dated May 29, 2002 does not amend the LC Plan. The second letter
from LCOG changes the initial April 19, 2002 position by stating "that Jasper County doesn't
object to SCDHEC making a permitting decision for a C and D Landfill for T&T Disposal, LLC
of Hardeeville prior to completion of the new plan." Again, as with the April 19, 2002, letter,
such a statement in not an amendment to the LC Plan. Rather, at best, the letter is notice to
DHEC that Jasper County does not object to DHEC granting the T&T permit. A letter from a
single county which expresses no objection to a permit cannot morph into an amendment to a
regional plan.
In an attempt to avoid the conclusion that the LC Plan has not been amended to include the T&T
landfill, DHEC and T&T argue that Jasper County has its own plan with that plan simply
incorporated within the LC Plan. From that position, DHEC and T&T argue that Jasper County
has amended its plan to allow the landfill. I cannot agree.
Beyond all doubt, the LC Plan is a regional solid waste management plan. See S.C. Code Ann.
Sec. 44-96-40(39) (a regional plan "means a solid waste management plan prepared, approved,
and submitted by a group of counties in South Carolina pursuant to Section 44-96-80."). In
particular, it is the regional plan which includes Jasper County since it was "endorsed" by the
counties of Beaufort, Colleton, and Jasper. Those endorsements are memorialized by letters
from each of the respective governing bodies including Jasper County.
Within the context of SWPMA, there is no separate solid waste management plan for Jasper
County since such a plan can exist only if submitted by a single county. See S.C. Code Ann.
Sec. 44-96-40(7) (a county plan "means a solid waste management plan prepared, approved, and
submitted by a single county pursuant to Section 44- 96-80."). In this case, even a cursory
review of the LC Plan shows the plan is regional in scope and is not a single county plan.
Unquestionably, the document reveals the intent of the regional endorsing governments to join
the LC Plan to coordinate their activities as opposed to operating separate plans. Such intent
aligns the LC Plan with the stated purposes of SWPMA which "encourages local governments to
pursue a regional approach to solid waste management." S.C. Code Ann. Sec. 44-96-20(B)(14).
Moreover, the LC Plan furthers the policy of this state which is to encourage a regional approach
to solid waste management. S.C. Code Ann. Sec. 44-96-50(C).
Accordingly, against this backdrop of intent for regional cooperation, of compliance with the
regional goals of SWPMA, and of the specific endorsement by Jasper County of a regional plan,
the evidence of the existence of a single county solid waste disposal plan for Jasper County is
simply unpersuasive. There being no single county plan for Jasper County, the T&T landfill is
inconsistent with the LC Plan, and the permit must be denied.
In reaching such a conclusion, I recognize that Jasper County's actions beginning as early as
October 1997 have been based on the premise that Jasper County believed it was amending some
plan that would allow the T&T landfill. However, the only plan on file with DHEC relevant to
the T&T landfill is the LC Plan, and that plan has not been amended by LCOG.
Further, the LC Plan has not been amended by Jasper County. Again, I recognize that DHEC
has “penciled in” what it believed were amendments to the plan and that DHEC did so since it
believed SWPMA allowed such. While DHEC’s interpretations are entitled to “the most respectful
consideration and should not be overruled without cogent reasons” (Faile v. S.C. Employment Security
Comm’n., 267 S.C. 536, 230 S.E.2d 219 (S.C. 1976)), such positions must not be applied when
cogent reasons require a different position. See Stone Mfg. Co. v. South Carolina Employment
Sec. Comm'n, 219 S.C. 239, 64 S.E.2d 644 (1951) citing F. W. Woolworth Co. v. United States,
91 F.2d 973, 976 (2d. Cir. 1937) ("At most, administrative practice is a weight in the scale, to be
considered, but not to be inevitably followed. * * * While we are of course bound to weigh
seriously such rulings, they are never conclusive."). Here, cogent reasons exist to deviate from
DHEC’s practice.
First, DHEC’s view of how a regional plan is to be amended is inconsistent with the intent of
S.C. Code Ann. Sec. 44-96-80(O). That statute explains that "[a]ny amendments to a . . .
regional solid waste management plan must be adopted . . . in the same manner as provided for
in the initial plan." While the initial plan does not specifically state how the plan is to be
amended, nonetheless, the plain intent of Sec. 44-96-80(O) is that amendments are to be adopted
in the same manner that was used to adopt the initial plan. Here, that means that since the
regional plan was adopted by a multi-party endorsement, any amendments must be adopted in
the same manner.
Second, deviation from DHEC’s view is proper since its position provides an anomalous result.
DHEC’s position, carried out with no authorization from the initial agreement, allows the
unilateral actions of a single party to become the means for amending an agreement that required
a multi-party endorsement to becoming effective. Such a position is inconsistent with the
regional goals of the plan and of SWPMA. Thus, there being no amendment to the LC Plan to
allow the T&T landfill, the issuance of a permit for the T&T landfill is inconsistent with the
1994 LC Plan.
3. Reforming The Permit
The conclusion reached here is that the T&T landfill is inconsistent with the applicable solid
waste management plan. Therefore, the permit must be denied. There being no permit, the issue
of whether to "reform" the permit by deleting a final disposal capacity of approximately 2.2
million cubic yards and inserting a disposal capacity of 2.2 million cubic feet is not reached.
IV. Order
The permit sought by T&T for a construction, demolition, and land-clearing debris landfill
permit for the Snake Road area in Jasper County, South Carolina is denied.
AND IT IS SO ORDERED
______________________
RAY N. STEVENS
Administrative Law Judge
Dated: March 15, 2005
Columbia, South Carolina |