ORDERS:
ORDER
This
case arises from the denial of an application by Petitioner, Spectre, LLC, for
a storm water (also called “land disturbance”) permit by the Department of
Health and Environmental Control (“DHEC”). DHEC denied the permit solely
because its staff concluded that the proposed project’s impact on an area of
isolated wetlands violated the policies set out in the S.C. Coastal Management
Program. It was uncontested that the application for the permit met all
requirements of the South Carolina Storm Water Management and Sediment
Reduction Act, S.C. Code Ann. § 48-14-10, et seq. and the regulations
promulgated under that statute at S.C. Reg. 72-300, et seq. The parties
informed the Court during a pre-trial conference that there were no questions
of material fact at issue in the case and that the questions before the Court
were entirely ones of law. The parties thereafter filed cross motions for
summary judgment, DHEC and Intervenors (hereinafter simply “DHEC”) filing a
joint motion.
Spectre’s
motion asserted that DHEC lacks statutory or regulatory authority to apply the
policies of the S. C. Coastal Management Program (the “CMP”) to make
substantive decisions on the issuance of storm water permits for projects which
impact isolated wetlands and that it is entitled to an order requiring that the
permit requested be issued by DHEC with no requirements for mitigation of
wetland impacts. DHEC argued that the policies in the CMP may be applied by
DHEC in the same way as regulations promulgated pursuant to the S.C
Administrative Procedures Act and that the policies applied to the Spectre
site.
After
considering the evidentiary materials and arguments of the parties and for the
reasons set out below, I find that DHEC does not have statutory or regulatory
authority to apply the CMP policies to Spectre’s permit and, therefore, Spectre
is entitled as a matter of law to be issued the storm water permit for which it
applied without any conditions related to mitigation for wetland impacts.
DHEC’s denial, therefore, should be reversed pursuant to S.C. Code Ann. § 1-23-380(A)(5)(a-f) (Supp. 2006).
I
PROCEDURAL
HISTORY
On February 14, 2006, Spectre, LLC, the Petitioner, filed an application for a storm water
permit with the OCRM Division of SCDHEC. On July 6, 2006, DHEC denied the permit. Spectre filed a request for final review of the permit denial with the
DHEC Board on July 13, 2006 pursuant to the S.C. Administrative Procedures Act.
A Final Review was conducted before the full DHEC Board on August 10, 2006 at which the Board affirmed denial of the permit. Spectre filed a timely appeal with
this Court on August 30, 2006. The parties submitted evidentiary material in
support of their respective motions for summary judgment and extensive legal
briefs. Oral argument was heard by the Court at a hearing on December 3, 2007.
II
UNDISPUTED
FACTS
A. SPECTRE’S PROJECT
The
storm water permit requested by Spectre, LLC is for clearing and drainage of a
62.93 acre site in Horry County necessary to the development of the site for
commercial/retail purposes. The site is located immediately north of the
Horry/Georgetown County line and adjacent to U.S. Highway 17, lying on the west
side of the highway. (Pet. Exh. 20, Corps of Engineers Wetland Plat; Pet. Exh.
21, Spectre Storm Water Permit Application). The storm water regulations at
S.C. Reg. 72-300 require detailed engineering analysis and information concerning
routing and management of storm water from the site. Principle concerns
reflected in the regulations are sediment transport and erosion control as well
as flood control. Prior to denial of the permit, DHEC declared the permit
application filed by Spectre to be complete and sufficient with respect to the
requirements of the storm water regulations. There is no dispute that Spectre’s
application complied in every particular with the storm water regulations and
that, if only these regulations were applied to consideration of the
application, the permit should have been issued. (Pet. Exh. 19, DHEC Board
Final Decision).
It
is uncontested that DHEC’s denial of the permit was based solely on impacts of
the proposed project to a 31.76 acre portion of the site which meets the
criteria of the 1987 manual used by the federal government to classify what the
manual refers to as “wetlands.” (Pet. Exh. 19, DHEC Board Final Decision). (To
be classified as a wetland under the manual, a site must possess three
characteristics – soil with certain physical properties associated with
periodic saturation, vegetation capable of living in saturated soil conditions,
and water present on the site or within twelve inches of the surface of the
site at least fourteen days during the growing season). Rapanos v. U.S., 126 S.Ct. 2208, at 2237 (2006).
The
U.S. Army Corps of Engineers verified that the site is not connected to the
surface water tributary system – that it is “isolated” – and, therefore, is not
subject to federal jurisdiction pursuant to Section 404 of the Clean Water Act,
33 USC Sec. 1344. (Pet. Exh. 20, Corps of Engineers Wetland Plat). The Corps’
renunciation of its jurisdiction was necessitated by the decision of the U.S.
Supreme Court in Solid Waste Authority of Northern Cook County v. U.S. Army
Corps of Engineers, 531 U.S. 159, 121 S.Ct. 675, 148 L.Ed.2d 576 (2001),
generally referred to as the “SWANCC” case, holding that the federal government
did not have authority to regulate wetlands isolated from the surface water
system of creeks, streams and rivers which drain into traditional navigable
waters. For sixteen years prior to this decision, the Corps and the U.S.
Environmental Protection Agency regulated isolated wetlands by asserting that
Section 404 of the Clean Water Act required a permit from the Corps for the
discharge of fill material into such areas. (Pet. Exh. 26, Excerpt from Law
of Wetlands Regulation, William L. Want).
B. PERMIT
DENIAL
DHEC
denied Spectre’s permit based on its staff’s conclusion that the impacts to the
wetland on the site violated several policies included in the S.C. Coastal Zone
Management Program (CMP). (DHEC letter of July 6, 2006, Attached to Spectre Request for Contested Case Hearing). All of these polices relate either to
general resource values or to wetlands. None relate to storm water management
plans or storm water permits. The policies listed were: Chapter III, Sec. C.3.1(1)(b); Chapter III, Sec. C.3.1(7); Chapter III, Policy Section IV.1(b) and (c);
Chapter III, Policy Section VII.A.1; and Chapter III, Policy Section XII.E.1.
In summary, these policies provide that projects that fill or otherwise destroy
wetlands should not be authorized. (Resp. Exh. 3, CMP at pages III-14, 40 and
73).
DHEC
claimed in its denial letter that the Spectre project was inconsistent with the
above policies and, therefore, with the CMP, requiring denial of the
application.
C. THE
SOUTH CAROLINA COASTAL MANAGEMENT PROGRAM
The
CMP was published by the South Carolina Coastal Council in 1978 to satisfy a
number of requirements, including, as the name implies, to serve as the
Environmental Impact Statement (“EIS”) for the federal approval and funding
aspect of the State program. (Resp. Exh. 3, CMP). It is uncontested that the
CMP was never promulgated in compliance with the Administrative Procedures Act.
(Pet. Exh. 8, DHEC Answers to Spectre Interrogatories). Indeed, the CMP was
published in the State Register on October 20, 1978 with this introductory notation:
THIS ISSUE OF THE STATE
REGISTER IS A SPECIAL ISSUE DEVOTED TO THE PUBLICATION OF THE COASTAL
PROGRAM OF THE SOUTH CAROLINA COASTAL COUNCIL FOR INFORMATION PURPOSES ONLY.
THE CONTENTS OF THIS ISSUE ARE PRINTED IN THE FORM SUBMITTED TO THE LEGISLATIVE
COUNCIL AND DO NOT CONSTIUTE OFFICIAL REGULATIONS AS DEFINED IN ACT 176 OF 1977.
(Pet. Exh. 24, Introduction to
State Register, Oct. 20, 1978).
The
CMP served to satisfy the goals set forth in the South Carolina Coastal Zone
Management Act, S.C. Code Ann. § 48-39-80, among which were the establishment
of a permitting system (called a “regulatory system”) for impacts to the
critical areas, subsection (A) along the coast and establishment of a system,
“whereby the department shall have the authority to review all state and
federal permit applications in the coastal zone, and to certify that these do
not contravene the management plan.” Subsection (B)(11). Regulations were
promulgated and are published at S.C. Code Reg. 30-1 governing issuance of
permits for alteration of critical areas. No regulations have ever been
promulgated which govern the review of all state and federal permit
applications for projects in the coastal zone. Instead, the S.C. Coastal
Council and its successor, the Ocean and Coastal Resource Management Division
of DHEC, made those decisions based solely on policies contained in the CMP
where they deemed “consistency certification” was necessary. (Pet. Exh. 8,
DHEC Answers to Spectre interrogatories; Pet. Exh. 2, Deposition of Carolyn
Boltin; Pet. Exh. 3, Deposition of John Hensel; Pet. Exh. 4, Deposition of
Richard Chinnis; Pet. Exh. 5, Affidavit of Christopher Holmes; Pet. Exh. 6,
Affidavit of Mary Shahid).
Every
permit application processed by the Army Corps under Section 404 of the Clean
Water Act for the filling of wetlands requires two certifications by DHEC
before the Corps may issue the permit. Section 401 of the Clean Water Act, 33
U.S.C. Sec. 1341, requires a “water quality certification” that the proposed
project will not contravene state water quality standards. (Pet. Exh. 12, DHEC
Emergency Regulation). DHEC’s decisions on water quality certifications are
governed by a set of regulations adopted in accord with the Administrative
Procedures Act, S.C. Code Section 1-23-10, et seq., and found at S.C. Code Reg. 61-101.
Similarly,
pursuant to the federal Coastal Zone Management Act, 16 U.S.C. Sec. 1456(c),
DHEC must certify that a project is consistent with the state’s Coastal
Management Program (“CMP”). As with the 401 certification, if “CZM
certification” is denied, or if conditions are attached to such certification
by DHEC, the decision is binding, as a matter of federal law, on the Army
Corps. 33 C.F.R. Part 320.3(b), 320.4(h), 325.2(b)(2).
As
originally published, the CMP specifically described the wetlands to which its
policies applied as only those which were contiguous to coastal rivers and
streams. The policies relied on by DHEC as authority to regulate the wetlands
at issue here are contained at Section III-73(e) of the CMP which contains this
finding:
In addition to the
extensive areas of salt and brackish marsh within the critical areas along the South Carolina coastline, the State’s coastal zone also contains over 60,000 acres of
fresh-water marshes. These wetlands further up the creeks and rivers, beyond
the reach of saltwater at high tides, have a great diversity of plant species.
They play a vitally important role in contributing nutrients to the waters
which eventually reach the estuarine system (the critical areas). Fresh-water
marsh areas are active filters for improving water quality, and since they
are linked with the downstream system, they affect water quality in the
critical areas. The fresh-water marshes are important flood buffers and also
function in maintenance of salinity levels in downstream estuaries.
(Pet. Exh. 25, Excerpts from CMP,
p. III-73) (emphasis supplied).
It
is not surprising that the original CMP referred only to contiguous wetlands.
At the time it was proposed in 1978, there was no federal permit requirement
which applied solely to isolated wetlands, as the Army Corps had issued a
blanket authorization for filling such areas. (Pet. Exh. 26, Excerpt from Law
of Wetlands Regulation, William L. Want). No state permit requirement
existed at that time which in any way applied to impacts to isolated wetlands. The
storm water permit requirement was not created by the General Assembly until
passage of the Storm Water Management and Sediment Reduction Act, S.C. Code Ann.
§ 48-14-10 in 1992.
In
1993, the CMP was amended through adoption of a set of “refinements.”
The refinements were also not promulgated as regulations in accord with the APA. Despite the clear language of Section III-73(e) of the CMP limiting its application to
those wetlands “linked with the downstream system” of coastal rivers and
creeks, the Coastal Council began to regulate any wetland which was subject to
the jurisdiction and regulation by the Army Corps. (Pet. Exh. 4, Deposition of
Richard Chinnis). Consequently, the 1993 refinements to the CMP provided that
such review applied only to wetlands under the jurisdiction of the Army Corps.
In the section entitled “Wetlands” on page 1, the Background paragraph says:
The Corps of
Engineers is mandated by Federal law to delineate wetlands. Once delineated by
the Corps of Engineers, Coastal Council manages the wetlands
through the policies contained in Chapter III of the State’s Coastal Zone Management
Program document.
(Resp. Exh. 11, CMP Refinements)
(emphasis supplied).
On
page 12, the refinements introduced a new policy governing mitigation of
wetland impacts:
The avoidance of
wetlands is preferable to mitigation. Mitigation of wetlands impacts is
considered only after all policies of the S.C. Coastal Council Program Document
and the Coastal Zone Management Act have been addressed and the mitigation plan
must be submitted by the applicant and approved by the Coastal Council for all
projects which (1) require a coastal zone consistency determination, and (2)
impact federally defined jurisdictional freshwater wetlands in the coastal zone, unless (3) the Coastal Council determines that the
impacts are so minimal as not to warrant mitigation.
(Resp. Exh. 11, CMP Refinements)
(emphasis supplied).
When
the SWANCC decision removed isolated wetlands from federal jurisdiction
in 2001, DHEC lost the ability to review Section 404 permit applications for
projects involving isolated wetlands. DHEC characterized this retreat of
federal regulation of wetlands as an emergency and promulgated an emergency
regulation for the purpose of restoring review for impacts to isolated wetlands
for both 401 water quality certification and coastal zone consistency
certification. (Pet. Exh. 12, DHEC Emergency Regulation). The authority for
promulgating the emergency regulation was the Administrative Procedures Act,
S.C. Code Ann. § 1-23-130. As required by the APA, DHEC attached to the
regulation an explanation of the emergency which they believed justified the
extraordinary step which included the following statement, “The SWANCC
decision held that the Corps does not have jurisdiction over isolated wetlands
and therefore removed the Department’s opportunity to issue water quality and
coastal zone consistency certifications for activities in those areas.” (Pet.
Exh. 12, DHEC Emergency Regulation) (emphasis supplied).
The
agency’s solution to the loss of DHEC’s and OCRM’s ability to review impacts to
isolated wetlands through their respective certification programs was to adopt
the federal method for delineating a wetland, and require that any State
permitted activity impacting areas meeting this criteria for a wetland be
certified as consistent with both State 401 water quality standards and (for
projects in the coastal counties) with CMP policies. Simply put, the emergency
regulation restored the same review of impacts to isolated wetlands by DHEC
which existed when a project required a Section 404 permit from the Army Corps,
by adding these certifications as requirements for State permits that impacted
wetlands not subject to Army Corps jurisdiction.
DHEC
did not submit the emergency regulation to the General Assembly and it expired
in May 2001. Citing the same reasons, DHEC proposed permanent regulations in
2003 giving it the power to regulate isolated wetlands outside of federal
jurisdiction and cited the same reasons. (Pet. Exh. 14, Summary Sheet for DHEC
Proposed Regulations; Pet. Exh. 15, DHEC Preamble to Proposed Regulations; Pet
Exh. 16, Excerpt of Transcript of DHEC Public Hearing on Proposed Regulations).
These regulations were not adopted by the General Assembly.
Despite
its repeated declarations that the state lacks authority over wetlands not
regulated by the federal government, DHEC proceeded to act as though it had such
authority. Since a storm water permit is required for most land disturbance
activities, DHEC began to regulate impacts to isolated wetlands by denying
storm water permit applications or requiring mitigation for wetland impacts as
a condition for issuance of these permits. (Pet. Exh. 8, DHEC Answers to
Spectre Interrogatories).
In
2007, the S. C. Supreme Court decided the case of Responsible Economic
Development v. DHEC, 371 S.C. 547, 641 S.E.2d 425 (2007), in which it held
that DHEC lacked the statutory authority to employ either the Pollution Control
Act or the Anti-degradation regulations to make decisions on applications for
storm water permits. Since that decision, DHEC has not employed storm water
permits to regulate impacts to wetlands in the non-coastal counties. In the
coastal counties, however, DHEC has continued to regulate impacts to isolated
wetlands through application of what it asserts are the legally binding requirements
of the CMP’s policies. (Pet. Exh. 8, DHEC Answers to Spectre Interrogatories;
Pet. Exh. 7, Affidavit of David Stevens).
It
is undisputed that these policies are being employed by DHEC as if they were
regulations promulgated pursuant to the Administrative Procedures Act. Both
Earl Hunter, DHEC Commissioner, and Carolyn Boltin, Deputy Commissioner of the
OCRM Division, testified that the agency regards these policies as having the
“force and effect of law”, just like regulations. DHEC admitted the same thing
in its Answers to Petitioner’s Interrogatories. (Pet. Exh. 8, DHEC Answers to
Spectre Interrogatories; Pet. Exh. 1, Deposition of Earl Hunter; Pet. Exh. 2,
Deposition of Carolyn Boltin). Despite this admission and these declarations,
the CMP is not contained in the S. C. Code of laws or published in any
compendium of state laws and regulations. They are available to the public only
in abbreviated form from DHEC itself.
While
applied by DHEC as if they were regulations, the CMP policies are not written
as regulations. They lack clarity and specificity on many points and lack
definitions of many key terms. They contain, most significantly, no definition
of what constitutes a wetland or a process adopted by the state for delineating
a wetland. It is uncontested that DHEC simply accepts designation by the Army
Corps of areas as a wetland. (Pet. Exh. 2, Deposition of Carolyn Boltin; Pet.
Exh. 3, Deposition of John Hensel; Pet. Exh. 8, DHEC Answers to Spectre
Interrogatories).
III
DECISION
Summary Judgment is proper when there is no issue as to any
material fact and the moving party is entitled to a judgment as a matter of
law. Rule 56(c), SCRCP; Helms Realty,
Inc. v. Gibson-Wall Co., 363 S.C. 334,
340, 611 S.E.2d 485, 488 (2005). To determine whether any triable
issues of fact exist, the Court must consider the evidence and all reasonable
inferences in the light most favorable to the non-moving party. Law v. S.C.
Dep't of Corr., 368 S.C. 424, 434, 629 S.E.2d 642, 648
(2006). When plain, palpable, and indisputable facts exist on which
reasonable minds cannot differ, summary judgment should be granted. Ellis v.
Davidson, 358 S.C. 509, 518, 595 S.E.2d 817,
822 (Ct. App. 2004). The existence of a mere scintilla of evidence
in support of the nonmoving party’s position is not sufficient to overcome a
motion for summary judgment. Bravis v. Dunbar, 316 S.C. 263, 265, 449
S.E.2d 495, 496 (Ct. App. 1994). The party seeking summary judgment
has the burden of establishing the absence of a genuine issue of material
fact. McNair v. Rainsford, 330 S.C. 332, 341, 499 S.E.2d 488, 493
(Ct. App. 1998). With respect to an issue upon which the nonmoving party
bears the burden of proof, this initial responsibility may be discharged by
showing the trial court there is an absence of evidence to support the
nonmoving party’s case. Id.
Based
on the undisputed facts in the record, as explained below, the Court finds that
DHEC lacked authority to rely on the CMP policies to deny Spectre’s storm water
permit for two reasons. The CMP policies by their own terms do not apply to the
isolated wetland on the Spectre site. In addition, the CMP policies have not
been promulgated as regulations in compliance with the APA and, therefore, may
not be employed as binding norms by DHEC to render decisions on permit
applications, as was done in this case.
A. LIMITATIONS IN THE
LANGUAGE OF THE CMP POLICIES
It
is undisputed that the wetlands on the Spectre site are isolated and not
connected to the surface tributary system. The Army Corps, as the CMP policy
refinements acknowledge it is authorized to do, has delineated the wetlands on
the Spectre site and determined that they are isolated and outside of its
jurisdiction pursuant to the Clean Water Act.
The
CMP policies contained in the original 1978 CMP document relating to wetlands
outside the critical areas were specifically limited to, “fresh-water
marshes…wetlands further up the creeks and rivers, beyond the reach of
saltwater at high tides… Fresh-water marsh areas linked with the
downstream system,” which serve to protect the water quality of the
downstream critical areas. (Resp. Exh. 3, CMP at page III-73) (emphasis
supplied). An isolated wetland, like that on the Spectre site, unconnected to
the surface tributary system, does not meet this description of “fresh water
marshes” and “wetlands”. The policies set forth in Section III relied on by
DHEC, therefore, simply do not apply to the Spectre permit application.
Moreover,
the 1993 refinements, clearly limit application of the CMP policies to wetlands
over which the Army Corps has jurisdiction. The following statement on page one
of the refinements is unambiguous, “Once delineated by the Corps of
Engineers, Coastal Council manages the wetlands through the policies contained in Chapter III of the State’s Coastal Zone Management Program
document.” (Resp. Exh. 11, CMP Refinements) (emphasis supplied). The
requirements for avoidance of wetland impacts and mitigation of unavoidable
impacts DHEC cited in its denial of Spectre’s permit are set forth on page 12
of the refinements and specifically apply only when projects require
coastal zone consistency certification “and impact federally defined jurisdictional freshwater wetlands in the coastal zone.” (Resp. Exh. 11, CMP
Refinements) (emphasis supplied). This language absolutely limits application
of the CMP policies to wetlands over which the Army Corps exercises
jurisdiction.
DHEC’s
claim to authority over the isolated wetlands on the Spectre site is premised
entirely on its claim that the General Assembly approved both the 1978 CMP and
1993 refinements. Yet, in this case DHEC asks the Court to hold that it has
authority much broader than what it says was approved by the General Assembly –
in effect, to have the Court approve a substantial expansion of that authority.
An agency cannot change the limits of its authorization, even if it concludes
the change is necessary to achieve the purposes of the authorization. In Simkins
v. City of Gaffney, 431 S.C. 592, 315 S.E.2d 26 (Ct. App. 1993), the Court
of Appeals reiterated the principle that an ordinance or similar regulation may
not be amended by the passage of a resolution, but must be amended, “by another
ordinance or an instrument of equal dignity.” Accord, Lominick v. City of
Aiken, 244 S.C. 32, 135 S.E.2d 305 (1964), citing Central Realty Corp.
v. Allison, 218 S.C. 435, 63 S.E.2d 153 (1951), “to permit the previous
ordinance here...to be amended or repealed by the indefinite motion or
resolution above referred to would result, we believe, in repeated confusion.”
There
is equal reason for concern over the novel assertion by DHEC in this case.
DHEC has offered no justification for a retreat from the principle that
amendments to regulations, by whatever name, should only be approved through
the full legislative process.
The
terms of the policies do not permit review of isolated wetlands over which the
Army Corps does not have jurisdiction and, therefore, under the rule of Responsible
Economic Development, DHEC has no authority to use the policies to make
decisions on storm water permit applications involving impacts to isolated
wetlands over which the Army Corps does not exercise jurisdiction. DHEC’s
application of the policies to areas specifically outside their coverage is no
different from, “the case-by-case modification of regulatory requirements under
the Stormwater Act,” struck down by the Supreme Court in that case. It was,
therefore, an abuse of discretion for DHEC to base denial of Spectre’s permit
on the CMP policies.
B.
APPLICATION OF THE CMP POLICIES AS REGULATIONS
The
S.C. Administrative Procedures Act, at S.C. Code Ann. § 1-23-10 (4) defines a
regulation:
(4) “Regulation”
means each agency statement of general public applicability that implements or
prescribes law or policy or practice requirements of any agency. Policy or
guidance issued by an agency other than in a regulation does not have the force
and effect of law. The term “regulation” includes general licensing criteria
and conditions and the amendment or repeal of a prior regulation...
S.C. Code Ann.
§ 1-23-10 (4) (Rev. 2005).
The
S.C. Supreme Court has articulated a test to determine if a particular
statement of agency policy amounts to a, “statement of general public
applicability that implements or prescribes law or policy…Whether a particular
agency proceeding announces a rule or a general policy statement depends upon
whether the agency action establishes a binding norm.” Home Health Service,
Inc. v. SC Tax Commission, 312 S.C. 324, 440 S.E.2d 375 (1994), citing Ryder
Truck Lines, Inc. v. U.S., 716 F.2d 1369 (1983).
It
is undisputed that DHEC denied Spectre’s application for a storm water permit
because its staff concluded that it violated policies contained in the CMP
quoted in the July 6, 2006 denial letter. All of DHEC’s witnesses testified
that these policies are employed by DHEC as the criteria by which the agency
decides whether to approve a project (and allow it to be permitted), and upon
what conditions. The 1993 refinements to the policies, cited by DHEC in its
denial letter, include the rules governing how permit applicants are required
by DHEC to mitigate for wetland impacts.
The
policies contained in the CMP have been used as regulations in every sense, as
they are the sole criteria employed by the agency to determine whether it will authorize
a proposed project. Nevertheless, DHEC has taken the position that the CMP
policies need not be promulgated in accord with the Administrative Procedures
Act’s requirements for regulations. It is enough, DHEC argues in its memoranda,
for these regulations to have been in the text of the CMP, and if that document
has been adopted in accord with the Coastal Zone Management Act, the policies
may be enforced as if they are valid regulations.
A
review of the language of the Coastal Zone Management Act itself reveals no
support for this argument. The Act at Section 48-39-80 required the
establishment of a Coastal Management Program to include a long list of
different functions. Many of the requirements were data gathering, such as
section (B)(1) to identify resources and land uses, and (B)(4) to inventory
areas of critical state concern in the coastal zone. Others were planning
mandates, such as (B)(2) to evaluate resources in terms of quality, quantity
and capability for use, and (D) to consider planning and review of water
quality standards and classifications.
Also
required in section (A) was the creation of, “a regulatory system which the
department shall use in providing for the orderly and beneficial use of the
critical areas,” defined at Section 48-39-10(J) of the Act as those areas of
water and marsh closest to the sea. For this “regulatory” system, the Act in
Section 48-39-130(B) required the agency to promulgate regulations in accord
with the APA. Finally, the Program was to include a, “system whereby the
department shall have the authority to review all state and federal permit
applications in the coastal zone, and to certify that these do not contravene
the management plan.” Subsection 48-39-80 (B)(11). The CMP describes how all of these mandates were to be carried out.
DHEC
seems to argue that the CMP document was devoted only to establishment of the
last mandate – the consistency certification process – while the critical area
permitting system was established independently in regulations. In fact, the
CMP document describes all aspects of the program listed in
48-39-80. At page III-12, it summarizes the permitting system for critical area
impacts, which it notes will be governed by regulations separately
promulgated by the agency.
There
is nothing in the Act itself or the CMP implying that regulations for the
consistency certification process are to be promulgated in the CMP document
itself. In fact, in the Legal Authorities section of the CMP, at p.V-1 and 2,
entitled, “Authority Outside Critical Areas,” it says “All agencies currently
exercising regulatory authority in the coastal zone shall administer such
authority in accordance with the provisions of this act and rules and
regulations promulgated thereunder.’” (Resp. Exh. 3, CMP at page V-1)
(emphasis supplied). This language can only refer to coastal zone consistency
certification by the agency of state permits in the coastal counties. The CMP
document itself, therefore, contemplated promulgation of regulations governing
certification as well as regulations governing critical areas.
It
has long been held that regulatory bodies are creatures of statute whose powers
may not be derived from mere inference. “Their power must be founded upon
language in the enabling acts which admits of no other reasonable
construction.” Piedmont and Northern Railroad Co. v. Scott, 202 S.C.
207, 24 S.E.2d 353 (1943), which explained the principle:
Such bodies being
unknown to the common law, and deriving their authority wholly from
constitutional and statutory provisions, will be held to possess only such
powers as are conferred, expressly or by reasonably necessary implication, or
such as are merely incidental to the powers expressly granted. Any reasonable
doubt of the existence in the Commission of any particular power should
ordinarily be resolved against its exercise of the power. And purely
administrative functions are readily distinguishable from the making of
regulations affecting substantial rights, which being in derogation of the
common law must be derived from constitutional or statutory provisions.
Piedmont and Northern Railroad Co., 24 S.E.2d at 360. Accord: Captain’s
Quarters Motor Inn, Inc., supra.; Mungo v. Smith, 289 S.C.560, 347
S.E.2d 514 (Ct. App. 1986); SCE&G v. PSC, 275 S.C. 487, 272 S.E.2d
793 (1980); Bunch v. Cobb, 273 S.C. 445, 257 S.E.2d 225 (1979); Brooks
v. State Board of Funeral Service, 271 S.C. 457, 247 S.E.2d 820 (1978); and Black River Electric Co-op, Inc. v. PSC, 238 S.C. 282, 120 S.E.2d 6
(1961).
The
S.C. Supreme Court has applied this principle to invalidate actions by DHEC
(and DHEC’s predecessor, the Coastal Council) found to be beyond their
statutory authorities. Captain’s Quarters Motor Inn, Inc., supra. held
the Coastal Council could not employ a policy regarding damage assessment to
evaluate sea wall permits as it was never promulgated as a regulation. In Brown v. DHEC, the court struck down an interpretation – an internal
policy – of DHEC regarding the storm water statute and regulations which the
court found to be contrary to the wording of the statute and associated
regulations. Most recently, and, perhaps, most significantly, in Responsible
Economic Development, supra., the court held that DHEC lacked authority to
evaluate storm water permits using either the Pollution Control Act or the
anti-degradation regulations published at S.C. Reg. 61-68.
DHEC
asserts that as the CMP was published in accord with the procedure set forth in
the Coastal Zone Management Act, it was unnecessary for the policies to be
promulgated as regulations in accord with the APA. To do so, DHEC argues, would
have been redundant. Comparison of the requirements of the Coastal Zone
Management Act and the APA, both as it existed in 1978 when the original CMP
was published, and in 1993 when the refinements were published, shows that this
is not the case. There are significant substantive requirements required by the
APA which were not required for publication of the CMP.
The
Coastal Zone Management Act required the CMP to be presented in hearings held
around the state, that notice be given in advance of the hearings and that all
documents related to its preparation be made available for public review. After
public review and preparation of the final document, it was to be “approved” by
the governor and the General Assembly with no specifics provided for an
approval process.
The
1978 APA required similar public review and hearings, but also required
specific notice to the public that regulations were being promulgated. The APA also required submission of the final text of proposed regulations to the appropriate
committees in both houses of the General Assembly. Neither of the latter
requirements was satisfied by the process by which the original CMP was
published. In fact, when it was published for public review, the notice
specifically announced that no regulations were being promulgated.
Similarly,
the APA in effect in 1993 required notice to the public that regulations were
being promulgated and that a specific and detailed filing and committee review
process be followed for General Assembly approval of regulations. The 1993
refinements, like the original CMP, were not promulgated as proposed
regulations and the General Assembly did not process them as such. It is the
complete lack of notice that regulations were being published which most
distinguishes the process followed in publishing the CMP and its refinements
from that required for promulgating regulations. Absent a specific legislative
provision, not present here, the Court finds that there is no support for the
suggestion that the General Assembly intended regulations to be promulgated
without specific notice that regulations having the full force and effect of
law were being proposed and legislative consideration consistent with proposed
regulations.
The
CMP policies at issue are like the policy involved in Captain’s Quarters Inn,
the CMP policies employed by DHEC to deny Spectre’s permit application, are
“binding norms”, and as such may not be applied to make substantive permit
decisions until they are promulgated as regulations pursuant to the APA. Like the anti-degradation regulations at issue in Responsible Economic
Development, there is no statutory authority for DHEC to deny storm water
permits because they do not satisfy the requirements of the CMP policies.
DHEC’s denial of Spectre’s permit was, therefore, arbitrary and capricious,
outside the agency’s authority, and as such, DHEC’s action was null and void.
As the storm water permit application filed by Spectre satisfied the
requirements of the storm water regulations at S.C. Reg. 72-300, et seq.,
Spectre was entitled to a storm water permit as a matter of law.
C. SPECTRE IS ENTITLED TO A
PERMIT BY OPERATION OF LAW.
As
the CMP policies relied upon by DHEC to deny Spectre’s permit do not apply to
its permit by their own terms and as the policies are not properly promulgated
regulations, DHEC acted without any legal authority in basing its denial of the
permit on those policies and employing them as if they were regulations
promulgated pursuant to the APA. DHEC’s decision must, therefore, be reversed
pursuant to S.C. Code Sec. 1-23-380(A)(a-f) as it was made in violation of the APA, exceeded the authority conferred on DHEC by S.C. Code Sec. 48-14-10, et
seq., was made using an unlawful procedure (application of policies as if they
were regulations without promulgating them as such), was clearly erroneous as
it was premised improperly on the CMP policies, and was arbitrary, capricious
and an abuse of discretion for the same reason
Spectre’s
storm water permit was complete and satisfied the storm water permit
regulations at S.C. Reg. 72-300 at the time it was improperly denied on July 6, 2006. Like the permit applicant in Responsible Economic Development, Spectre
was entitled to a storm water permit as a matter of law issued solely in accord
with those regulations. S.C. Reg. 72-305(M) provides that a storm water permit
will be considered approved if DHEC does not take action within twenty working
days of receiving a complete application. In this case, DHEC’s action was more
than an abuse of discretion; it was in excess of its legal authority. For that
reason, the Court finds that Spectre is entitled to have its storm water permit
deemed approved as of a date twenty working days after July 6, 2006. The Court
further finds that any wetland mitigation proposed by Spectre may not be made a
part of its obligations under its storm water permit as DHEC lacked any authority
to require such mitigation either in S.C. Code Sec. 48-18-10, et seq. or S.C.
Reg. 72-300.
IT
IS SO ORDERED.
___________________________
John
D. McLeod
Administrative
Law Judge
February 19, 2008
Columbia, South Carolina
The power exercised here by OCRM is tantamount
to a “taking”. The authority to do so requires the dignity of a statute or duly
promulgated regulation that is codified as part of the Code of Laws/Regulations
of South Carolina to which the public has ready access. Commerce in this state
depends, in an important degree, upon the business community being able to make
decisions based on reasonable expectations derived from clear and accessible
statutes and regulations. Likewise, the environmental community and the
agencies charged by the State with the protection of the environment need the
same clear and accessible statutes to carry out their functions.
|