South Carolina              
Administrative Law Court
Edgar A. Brown building 1205 Pendleton St., Suite 224 Columbia, SC 29201 Voice: (803) 734-0550

SC Administrative Law Court Decisions

CAPTION:
South Carolina Electric & Gas Company vs. SCDHEC, et al

AGENCY:
South Carolina Department of Health and Environmental Control

PARTIES:
Petitioner:
South Carolina Electric & Gas Company

Respondent:
South Carolina Department of Health and Environmental Control and Brett Bursey
 
DOCKET NUMBER:
01-ALJ-07-0486-IJ

APPEARANCES:
n/a
 

ORDERS:

CONSENT ORDER

This matter comes before the Administrative Law Judge Division upon Respondent Bursey's Notice of Appeal challenging any and all permits granted to SCE&G for its Saluda Dam Remediation Project. SCE&G filed a Motion for Injunctive Relief seeking, inter alia, relief from any automatic stay that may have been applicable to activities authorized by the permits as a result of Respondent's appeal. With the consent of the parties, the Court delayed a hearing on the Motion while the parties attempted to resolve Respondent Bursey's challenge to the permits. The parties have agreed to settle this matter with the execution of this Consent Order.

IT IS THEREFORE ORDERED, with the consent of the parties, as follows:

1. SCE&G shall inspect all silt fencing presently at the site and make repairs where necessary.

  • SCE&G shall place additional geotextile in the area adjacent to Outfall # 2.
  • SCE&G shall continue to water the additional hydroseeded areas around Outfall #2 every day until the areas are stabilized.
  • All disturbed slopes outside the borrow pit of 3:1 (h:v) slope or greater will be stabilized by installing geotextile and seeding. Seeded areas shall be watered as necessary for growth.
  • All other areas of disturbed soil shall be reseeded and watered as necessary to maintain effective, stable cover.
  • Within 48 hours of each rainfall event which exceeds 0.25 inches in 24 hours, or at least once every two weeks, whichever is less often, SCE&G shall inspect, clean of accumulated sediment as necessary, and repair all silt fences and sediment control devices until site stabilization has been achieved.
  • Within 12 hours after each rainfall event which exceeds 0.25 inches in 24 hours, SCE&G shall obtain grab samples from the stream below the outfalls depicted on SCE&G's Phase III Test Program Erosion & Sediment Control Plan maps which have the potential to discharge to the Saluda River. If there is no flow from an outfall as a result of a rainfall event, then SCE&G shall so certify and shall not be required to obtain a stream sample(s) below that outfall. SCE&G shall have any samples it obtains analyzed for total suspended solids (TSS) employing procedures and methods specified in the most recent EPA-approved protocol. The results of the sampling and analysis shall be forwarded to Respondents. Field notes and laboratory reports relating to the sampling shall be maintained by SCE&G for a period of one year and made available to the parties upon request.
  • SCE&G shall install baffles or forebays in Stormwater Ponds 1 and 2 to increase detention time. SCE&G shall also modify the riser barrel outlet structures in each pond to add a floating skimmer device.
  • SCE&G shall use active management techniques, including adjustment of the moisture level in the crusher and employment of best construction practices relating to dust suppression, to control fugitive dust at the site.
  • Upon reasonable notice following a rain event which exceeds 0.25" in 24 hours, or once per month, whichever is more frequent, SCE&G shall permit site access and inspection by Respondent Bursey or his designee. Bursey shall not, without specific permission of SCE&G, enter upon property owned by SCE&G at the dam remediation site or across the spillway from the dam remediation site.
  • Within five (5) days of the date of this Order, Bursey shall withdraw his appeal of the permits issued to SCE&G for the Saluda Dam Remediation Project.
  • Any party may bring an action in the Administrative Law Judge Division to compel compliance with the terms of this Consent Order.

AND IT IS SO ORDERED.



__________________________________

MARVIN F. KITTRELL

Chief Administrative Law Judge

December 10, 2001

Columbia, South Carolina



WE CONSENT:









______________________________

Robert Guild

314 Pall Mall

Columbia, South Carolina 29201

Phone (803) 252-1419

Fax (803) 254-1419



Attorney for Brett Bursey









______________________________

Alexander G. Shissias

Office of General Counsel

South Carolina Department of Health

and Environmental Control

2600 Bull Street

Columbia, South Carolina 29201

Phone (803) 898-3349

Fax (803) 898-3367



Attorney for South Carolina Department of Health

and Environmental Control









______________________________ ___________________________

Thomas G. Eppink Elizabeth B. Partlow

Assistant General Counsel Ogletree, Deakins, Nash,

SCANA Corporation Smoak & Stewart, P.C.

1426 Main Street, MC-130 1501 Main Street, Suite 600

Columbia, SC 29218 Post Office Box 11206

Columbia, South Carolina 29211

Phone (803) 252-1300

Fax (803) 254-6517



Attorneys for South Carolina Electric & Gas Company


Brown Bldg.

 

 

 

 

 

Copyright © 2024 South Carolina Administrative Law Court