ORDERS:
FINAL ORDER AND DECISION
I. Introduction
Citizens for Responsible Growth in Clemson (CRGC) seeks a contested case hearing to challenge a
decision by the South Carolina Department of Health and Environmental Control (DHEC) granting a
project under the stormwater management and sediment control permit to Wal-Mart Store # 3222,
Pickens County (Wal-Mart). The disagreement on the issuance of the permit places contested case
jurisdiction in the Administrative Law Judge Division under S.C. Code Ann.§§ 1-23-310 et seq. (Rev.
1987 & Supp. 2000) and 25 S.C. Code Ann. Regs. 61-72.201 (Supp. 2000). After considering the
evidence and applicable law, the permit must be granted.
II. Issues
1. Should a stormwater management and sediment control permit be granted to Wal-Mart allowing the
disturbance of thirty-eight acres at the corner of Highway 123 and Issaqueena Trail in Pickens County?
2. Should the permit be conditioned on more innovative stormwater management practices than that
submitted in Wal-Mart's stormwater management and sediment control plan?
III. Analysis
A. Propriety of Permit
1. Positions of Parties
CRGC argues that the stormwater permit should be denied for four reasons.
First, Wal-Mart's stormwater management and sediment control plan is inconsistent with the regulatory
standards for stormwater management and sediment reduction. More particularly, CRGC argues that
Wal-Mart has not demonstrated a non-erosive flow to the receiving waterway after land disturbance (26
S.C. Code Ann. Regs. 72-307(C)(4)(b) (Supp. 2000)), that the plan was inadequate in that it did not
cover the entire area to be developed (Regs. 72-307(C)(3) (Supp. 2000)), and that Wal-Mart has not
adequately demonstrated that it will achieve the required sediment removal efficiency for its sediment
basin during construction (Regs. 72-307(C)(5)(b) (Supp. 2000)).
Second, CRGC argues that the water quality standards under Regulation 61-101 require denial of the
permit. Specifically, CRGC argues that the construction of the proposed project will result in
cumulative adverse impacts on water quality and that a feasible alternative to the proposed project
exists which alternative significantly reduces the adverse impacts.
Third, the proposed project will constitute a nuisance to neighboring landowners.
Fourth, the proposed project will violate the ordinances of the City of Clemson.
DHEC and Wal-Mart disagree with CRGC. They both assert that Wal-Mart's stormwater management
and sediment control plan meets all of the applicable regulatory requirements. They also maintain that
Regulation 61-101 does not apply to the evaluation of an application for a stormwater permit. They
further maintain that issues such as nuisance and zoning must be considered in a separate action from
this contested case on the stormwater permit.
2. Findings of Fact
I find by a preponderance of the evidence the following facts:
Wal-Mart seeks to build a Supercenter store and parking lot within a 53 acre site at the corner of
Highway 123 and Issaqueena Trail in Pickens County, South Carolina. Wal-Mart plans to develop
approximately 38 acres of the site. Wal-Mart does not currently own the site; however, it has a pending
contract for the purchase of the 38 acres it plans to develop with the development contingent on
receiving the necessary approvals and permits to construct the project. (1) No current plans exist to
develop the remaining acreage on the site.
a. Permitting Agencies
At least two permitting agencies have a bearing upon the 38 acres involved in this case.
i. Federal Permitting
A portion of the 38 acres has been delineated as a wetland. Therefore, Wal-Mart needed a permit from
the U.S. Army Corps of Engineers before engaging in any land disturbing activities on the site. Wal-Mart obtained three nationwide permits from the Corps of Engineers on February 10, March 23, and
May 17, 2000 for land disturbance, installation of a sewer line across a tributary of Eighteen Mile
Creek, and installation of a storm water outfall pipe at the edge of the tributary.
There is some uncertainty regarding DHEC's issuance of a state water quality certification in
connection with the Corps of Engineers' issuance of the nationwide permits. Counsel for DHEC
indicated at the hearing during oral arguments that DHEC had issued a certification prior to the Corps'
issuance of the nationwide permits. However, no testimony or other evidence was presented on this
point. (2)
ii. State Permitting
On March 30, 2000, Wal-Mart applied to DHEC for a project permit under the stormwater management
and sediment control regulations. As part of the application, Wal-Mart submitted a stormwater
management and sediment control plan. The plan provides for construction of the store with an
accompanying parking lot and landscaping. All areas of the site will drain to a series of catch basins
conveying runoff through an underground storm drainage system to a detention pond. The detention
pond will be sized to handle the first half-inch of runoff from the drainage area, as well as the 2-year,
10-year, 25-year, and 100-year storm events. The pond will restrict stormwater runoff to pre-development discharge rates and it will have a staged outlet to manage each storm.
The pond will also serve as the sedimentation and erosion control pond during the construction phase of
the development. After the site has been stabilized, the silt will be removed from the pond and the pond
will be graded to its final configuration. A second basin will be installed on the south side of the site
and will be used for sediment control during construction only. It will be removed after the site is
stabilized.
b. Discharge Velocities
The design features in Wal-Mart's stormwater plan will reduce the discharge velocity to less than pre-development conditions. Mitchell Bohannon, III, an expert in stormwater management, erosion control
and water quality, testified that Wal-Mart's stormwater management system can accommodate a 100-year storm event and even reduces the velocity from the 100-year event, helping to reduce current
erosion in the receiving stream.
The original plans called for runoff to be discharged approximately 100 feet from the channel of a
tributary of Eighteen Mile Creek. However, following a public hearing on Wal-Mart's permit
application, DHEC required Wal-Mart to revise the design to discharge directly into the stream near the
edge of the property. The runoff will be angled in the direction of the stream's natural flow which will
reduce erosion.
Additionally, rip-rap, which will dispel the force of the discharge velocity, will be placed on both sides
of the stream. The use of rip-rap to slow the water is a common method used to achieve non-erosive
discharge velocities from a pipe system to an open channel. The runoff numbers used to size the rip-rap
are based on the entire drainage basin. The rip-rap has been sized to prevent bank erosion in a 25-year
storm event and will handle not only Wal-Mart's runoff, but also existing runoff.
c. Sediment Removal Efficiency
The soil loss model conducted by Wal-Mart's engineers originally contained an erodibility factor of
0.24 in the calculations to determine sediment removal efficiency. Using this factor, Wal-Mart's
engineers calculated a sediment removal efficiency of 87.75 % for the sediment basin, higher than the
80% removal efficiency required by Reg. 72-307.C(5)(b). This calculation is conservative since it does
not take into account the fact that additional measures such as silt fencing, inlet protection, and
diversion ditches will also be used in addition to the sediment basin to trap sediment. With these added
measures, the whole sediment removal system for the entire drainage area will have a sediment removal
efficiency that is even higher than that calculated by Wal-Mart's engineers.
CRGC's expert expressed concern that the 0.24 factor does not adequately reflect the actual sediment
loss that will occur from the extensive grading of the site. Therefore, Wal-Mart's engineers recalculated
the sediment removal efficiency with a higher erodibility factor of 0.28 and found that the sediment
removal efficiency was actually improved using this higher factor.
d. Issuance of permit
DHEC issued a project permit to Wal-Mart on May 24, 2000. On May 30, 2000, CRGC requested a
contested case hearing challenging DHEC's issuance of the permit.
3. Conclusions of Law
Based on the foregoing Findings of Fact, I conclude the following as a matter of law:
Under the facts of this case, the issue becomes determining whether DHEC properly applied the
applicable law in granting the permit.
a. Applicable Law in General
The Stormwater Management and Sediment Reduction Act charges DHEC with developing a State
Stormwater Management and Sediment Reduction Program. S.C. Code Ann. § 48-14-50(A) (Supp.
2000). To assist in accomplishing its task, the General Assembly authorized DHEC to promulgate
regulations governing, among other things, the types of activities requiring a stormwater management
and sediment control permit, specific design criteria and minimum standards and specifications, and
permit application and approval requirements. S.C. Code Ann. § 48-14-50(C) (Supp. 2000). Pursuant
to that authority, DHEC promulgated regulations governing standards for stormwater management and
sediment reduction. See 26 S.C. Code Ann. Regs. 72-300 through 72-316 (Supp. 2000).
In this case, Wal-Mart's proposed project will involve land disturbance of more than five acres.
Therefore, the provisions of 26 S.C. Code Ann. Regs. 72-305 and 72-307 (Supp. 2000) apply to Wal-Mart's permit application.
Additionally, Wal-Mart's proposed project will also involve a discharge of stormwater into waters of
the State and waters of the United States. (3) Therefore, Regulation 61-9, governing water pollution
control permits, applies to Wal-Mart's proposed project. Regulation 61-9 contains provisions for
implementation of the National Pollutant Discharge Elimination System (NPDES) Program under the
federal Clean Water Act and the South Carolina Pollution Control Act. Under the Program, DHEC may
issue a general permit governing a particular category of discharges within a geographic area and
regulating a particular category of sources. In the current case, DHEC notified Wal-Mart of its coverage
under General Permit #SCR104963 when it issued the stormwater management and sediment control
permit on May 24, 2000. None of the requirements of Regulation 61-9 are in dispute in this case.
b. Regulations: Standards For Disturbance of More than Five Acres
Standards for the evaluation of a proposed project disturbing more than five acres are found in
Regulations 72-305 and 72-307. Of the requirements listed in Regulation 72-305, none are in dispute.
Of the requirements identified in Regulation 72-307, the only ones in dispute are: (1) the stormwater
management plan for a specific project shall be based on the entire area to be developed (Regs. 72-307.C(3)); (2) discharge velocities shall be reduced to provide a non-erosive velocity flow from a
control measure or the velocity of the 10-year, 24-hour storm runoff in the receiving waterway prior to
the land disturbing activity, whichever is greater (Regs. 72-307.C(4)(b)); and (3) the sediment basin
must be designed to accommodate anticipated sediment loading from the land disturbing activity and
meet a removal efficiency of 80 percent suspended solids (Regs. 72-307.C(5)(b)).
i. Entire Area To Be Developed
Regs. 72-307.C(3) explains that stormwater management requirements for a specific project shall be
based on the entire area to be developed, or if phased, the initial submittal shall control that area
proposed in the initial phase and establish a procedure and obligation for total site control. CRGC
argues that there are parcels on the site that will be developed in the future that were not included in
Wal-Mart's stormwater plan. I disagree.
Here, the weight of the evidence shows that only 38 acres of the site will be developed and that Wal-Mart's stormwater plan adequately provides for these areas. Therefore, I conclude that Wal-Mart's plan
meets the requirement of Regs. 72-307.C(3).
ii. Discharge Velocity
Regs. 72-307.C(4)(b) sets forth a design criterion for the purpose of water quantity control. See introduction to 26 S.C. Code Ann. Regs. 72-307.C(4) (Supp. 2000) ("The following design criteria for
flow control is established for water quantity control purposes . . . ."). This criterion requires that
discharge velocities shall be reduced to provide a non-erosive velocity flow from a structure, channel, or
other control measure or the velocity of the 10-year 24-hour storm runoff in the receiving waterway
prior to the land disturbing activity, whichever is greater. In light of the criterion's stated purpose of
controlling water quantity, the language "whichever is greater" is obviously not intended to discourage
reduction of discharge velocity to even less than the velocity of the 10-year storm in the receiving
waterway or less than a non-erosive velocity. Rather, this language gives flexibility to stormwater plan
designers to reduce discharge velocity to merely the greater of the two stated velocities.
CRGC argues that Wal-Mart's stormwater plan fails to meet the criterion of Regs. 72-307.C(4)(b). I
disagree.
Here, the credible expert testimony indicates that the design features in Wal-Mart's stormwater plan
will reduce the discharge velocity to less than pre-development conditions. Mitchell Bohannon, III, an
expert in stormwater management, erosion control and water quality, testified that Wal-Mart's
stormwater management system can accommodate a 100-year storm event and even reduces the velocity
from the 100-year event, helping to reduce current erosion in the receiving stream. The runoff will be
discharged into the stream near the edge of the property and will be angled in the direction of the
stream's natural flow which will reduce erosion.
Additionally, rip-rap will be placed on both sides of the stream, which will dispel the force of the
discharge velocity. The runoff numbers used to size the rip-rap are based on the entire drainage basin.
The rip-rap has been sized to prevent bank erosion in a 25-year storm event and will handle not only
Wal-Mart's runoff, but also existing runoff.
CRGC also argues it is not possible to determine compliance with the non-erosive flow requirement of
Regs. 72-307.C(4)(b) without conducting a study or taking measurements of the receiving waterway
prior to development. However, the testimony establishes that a variety of models exist to calculate
velocity through various structures, networks, and channels, and that published tables exist of non-erosive velocities for different types of channels and structures. The testimony further establishes that
the common method used to assure non-erosive discharge velocities from a pipe system to an open
channel is to use rip-rap to slow the water. Thus, sufficient data exists to evaluate Wal-Mart's
stormwater plan against the requirement of Regs. 72-307.C(4)(b).
In conclusion, the testimony establishes that Wal-Mart's discharge velocities will actually be less than
the velocity of the 10-year 24-hour storm runoff in the receiving waterway prior to land disturbance.
Therefore, I conclude that Wal-Mart's plan meets the criterion of Regs. 72-307.C(4)(b).
iii. Sediment Removal Efficiency
Regs. 72-307.C(5)(b) requires a sediment basin to control stormwater runoff to a single outlet. The
sediment basin must be designed to accommodate anticipated sediment loading from the land disturbing
activity and meet a removal efficiency of "80 percent suspended solids or .5 ML/L peak settable solids
concentration, whichever is less." Further, Reg. 72-307.C(5)(b) requires the outfall device or system
design to take into account the total drainage area flowing through the disturbed area to be served by the
basin.
CRGC argues that the stormwater permit should be denied because Wal-Mart's plan contains an
erroneous erodibility factor in the calculation used to project the sediment removal efficiency of the
sediment basin. I disagree.
The soil loss model conducted by Wal-Mart's engineers originally contained an erodibility factor of
0.24 in the calculations to determine sediment removal efficiency. Using this factor, Wal-Mart's
engineers calculated a sediment removal efficiency of 87.75 % for the sediment basin, higher than the
80% removal efficiency required by Reg. 72-307.C(5)(b). Wal-Mart's experts opined that this
calculation is conservative in that it does not take into account measures in addition to the sediment
basin which will trap sediment, such as silt fencing, inlet protection and diversion ditches. With these
added measures, the whole sediment removal system for the entire drainage area will have a sediment
removal efficiency that is even higher than that calculated by Wal-Mart's engineers.
CRGC's expert expressed concern that the 0.24 factor does not adequately reflect the actual sediment
loss that will occur from the extensive grading of the site. Therefore, Wal-Mart's engineers recalculated
the sediment removal efficiency with a higher erodibility factor of 0.28 and found that the sediment
removal efficiency was actually improved using this higher factor. Therefore, Wal-Mart's failure to use
the 0.28 erodibility factor did not result in any undisclosed divergence from the standard set forth in Reg. 72-307.C(5)(b).
c. Applicability of Regulation 61-101
CRGC maintains that the water quality standards of Regulation 61-101 should be applied to the
evaluation of Wal-Mart's stormwater permit application. Specifically, CRGC argues that the
construction of the proposed project will result in cumulative adverse impacts on water quality and that
a feasible alternative to the proposed project exists which reduces these adverse impacts. I disagree.
The introductory paragraph to Regulation 61-101 states the following: "This regulation establishes
procedures and policies for implementing State water quality certification requirements of Section 401
of the Clean Water Act, 33 U.S.C. Section 1341." 25A S.C. Code Ann. Regs. 61-101.A(1) (Supp.
2000). A Section 401 water quality certification is not required as a prerequisite to the issuance of a
stormwater permit under Regulation 72-305. Rather, such a certification is the subject of a separate
proceeding and is a prerequisite to the Corps of Engineers' issuance of a permit under Section 404 of
the federal Clean Water Act. Because Regulation 61-101 pertains only to the implementation of state
water quality certification requirements of the federal Clean Water Act, the standards of Regulation 61-101 are not appropriate for application to a state stormwater permitting decision.
CRGC argues that it received neither notice nor an opportunity to be heard on the state water quality
certification issued in connection with the Corps of Engineers' permitting decisions on Wal-Mart's
proposed project. CRGC maintains that because it was denied due process in connection with the state
water quality certification decision, CRGC should be afforded an opportunity to be heard on the issues
arising under Regulation 61-101 in this contested case proceeding. I cannot agree.
In the instant matter, CRGC filed its written request for a contested case hearing challenging a specific
DHEC staff decision. (4) That decision decided a stormwater permit and not a Section 401 water quality
certification. (5)
If CRGC believes it has in fact been denied due process on a water quality certification
decision, then CRGC must seek the appropriate relief in a separate proceeding addressing DHEC's
alleged failure to give CRGC notice of the decision.
d. Nuisance, Takings, & Zoning Ordinance
CRGC argues that Wal-Mart's operation of its Supercenter store will unreasonably interfere with
neighboring residents' use and enjoyment of their property and will, therefore, constitute a nuisance.
CRGC maintains that where neighboring property owners' investment-backed expectations will be lost
due to Wal-Mart's permitted activities, CRGC may be entitled to assert a regulatory takings claim
against DHEC. Further, CRGC also argues that the proposed project violates the land use plan and
ordinances of the City of Clemson. For these reasons, CRGC argues, the permit should be denied. I am
unable to agree.
The issues of regulatory takings, nuisance, and violations of local zoning ordinances are not meaningful
considerations in a contested case proceeding deciding a stormwater permit request.
A "taking" is not a basis for denying a stormwater permit. Rather, proving that proper actions of a State
agency have deprived a land owner of all economically beneficial use of land is a basis for an action in
a forum authorized to award compensation for damages. For instance, the appropriate redress for a
takings claim lies with a jurisdiction having authority to award money damages. See Lucas v. South
Carolina Coastal Council, 112 S.Ct. 2886 (1992) (State must pay compensation to landowner where it
seeks to sustain regulation that deprives land of all economically beneficial use); Agins v. City of
Tiburon, 100 S.Ct. 2138, 2143, n. 2 (1980) ("Inverse condemnation is 'a shorthand description of the
manner in which a landowner recovers just compensation for a taking of his property when
condemnation proceedings have not been instituted.'").
Likewise, CRGC's claim of nuisance is not a basis for denying a stormwater permit. Rather, proving
such claims belong in a forum with jurisdiction to entertain actions founded in common-law nuisance or
nuisance, per accidens. See, e.g. LeFurgy v. Long Cove Club Owners Ass'n, Inc., 313 S.C. 555, 443
S.E.2d 577 (Ct.App. 1994) (where a master-in-equity had jurisdiction to declare a "tee box" a nuisance
and order an injunction) and O'Cain v. O'Cain, 322 S.C. 551, 473 S.E.2d 460 (Ct.App. 1996) (where
circuit court had jurisdiction to find that the presence of hogs was not a nuisance).
Furthermore, as to zoning, DHEC is not charged with the responsibility of establishing the land use mix
within an area. Rather, local zoning authorities hold the primary responsibility for land use decisions
and those authorities exercise wide discretion in decision making. See Bear Enterprises v. County of
Greenville, 319 S.C. 137, 459 S.E.2d 883 (Ct. App. 1995); Rushing v. City of Greenville, 265 S.C.
285, 217 S.E.2d 797 (1975). Indeed, local zoning ordinances constitute a separate hurdle for Wal-Mart
to overcome and the mere fact of the issuance of a stormwater permit does not prevent local zoning
authorities or appellate zoning bodies from prohibiting the proposed construction. All that is decided
here is that the stormwater management and sediment control permit is proper.
Accordingly, in the absence of an applicable state regulatory directive or standard (none being
established in this case), a state stormwater permit cannot be denied based on the arguments that the
granting of the permit will result in a "taking," will create a nuisance, or will conflict with local zoning
ordinances. Such positions must be litigated in other forums.
B. Permit Conditions
1. Positions of Parties
CRGC argues that adequately protecting existing water quality requires that Wal-Mart's proposed
project use significantly more innovative design criteria in its stormwater management plan than the
plan proposed by Wal-Mart delivers. CRGC maintains that the permit, if granted at all, must have
significant conditions imposed by DHEC in order to protect water quality.
Wal-Mart and DHEC disagree with CRGC's view. Wal-Mart and DHEC argue that no conditions on
the permit are needed since the stormwater management plan meets all applicable regulatory
requirements.
2. Findings of Fact
Wal-Mart's stormwater management and sediment control plan provides for construction of a store with
an accompanying parking lot and landscaping. All areas of the site will drain to a series of catch basins
conveying runoff through an underground storm drainage system to a detention pond. The detention
pond will be sized to handle the first half-inch of runoff from the drainage area, as well as the 2-year,
10-year, 25-year and 100-year storm events. The pond will restrict stormwater runoff to pre-development discharge rates and it will have a staged outlet to manage each storm.
The pond will also serve as the sedimentation and erosion control pond during the construction phase of
the development. After the site has been stabilized, the silt will be removed from the pond and the pond
will be graded to its final configuration. A second basin will be installed on the south side of the site
and will be used for sediment control during construction only. It will be removed after the site is
stabilized.
Wal-Mart's original plans called for runoff to be discharged approximately 100 feet from the tributary
channel. Following a public hearing on Wal-Mart's permit application, DHEC required Wal-Mart to
revise the design to discharge directly into the stream.
The design features in Wal-Mart's stormwater plan will reduce the discharge velocity to less than pre-development conditions. Wal-Mart's stormwater management system will accommodate a 100-year
storm event and will even reduce the velocity from the 100-year event, helping to reduce current erosion
in the receiving stream. The runoff will be discharged into the stream near the edge of the property and
will be angled in the direction of the stream's natural flow which will reduce erosion. Additionally, rip-rap will be placed on both sides of the stream, which will dispel the force of the discharge velocity. The
runoff numbers used to size the rip-rap are based on the entire drainage basin. The rip-rap has been
sized to prevent bank erosion in a 25-year storm event and will handle not only Wal-Mart's runoff, but
also existing runoff.
The soil loss model conducted by Wal-Mart's engineers originally contained an erodibility factor of
0.24 in the calculations to determine sediment removal efficiency. Using this factor, Wal-Mart's
engineers calculated a sediment removal efficiency of 87.75 % for the sediment basin, higher than the
80% removal efficiency required by Reg. 72-307.C(5)(b). Wal-Mart's experts opined that this
calculation is conservative in that it does not take into account measures in addition to the sediment
basin which will trap sediment, such as silt fencing, inlet protection and diversion ditches. With these
added measures, the whole sediment removal system for the entire drainage area will have a sediment
removal efficiency that is even higher than that calculated by Wal-Mart's engineers.
After CRGC's expert expressed concern that the 0.24 factor does not adequately reflect the actual
sediment loss that will occur, Wal-Mart's engineers recalculated the sediment removal efficiency with a
higher erodibility factor of 0.28. They found that the sediment removal efficiency was actually
improved using this higher factor.
3. Conclusions of Law
South Carolina Code Ann. § 48-1-50 (Supp. 2000) empowers DHEC to impose conditions on
environmental permits. DHEC has traditionally placed conditions on environmental permits in order to
ensure that a proposed project will meet the applicable regulatory requirements for the particular permit
being issued. In this case, no persuasive showing has been made that in the absence of special
conditions, the proposed project will not meet the applicable stormwater management and sediment
control regulations. In fact, the preponderance of the evidence shows that in some instances Wal-Mart's
stormwater plan exceeds the minimum regulatory requirements.
Therefore, no need exists to add conditions to the permit.
IV. Order
The South Carolina Department of Health and Environmental Control is directed to grant the request for
a stormwater management and sediment control permit sought by Wal-Mart for construction at
Highway 123 and Issaqueena Trail in Pickens County, South Carolina.
During and after construction on the site at Highway 123 and Issaqueena Trail, Wal-Mart shall carry out
those approved stormwater management practices set forth in its stormwater management and sediment
control plan.
Pursuant to Regulation 72-308.B, Wal-Mart shall perform or cause to be performed preventive
maintenance of all completed stormwater management practices set forth in its stormwater management
and sediment control plan to ensure proper functioning.
AND IT IS SO ORDERED
______________________
RAY N. STEVENS
Administrative Law Judge
Dated: May 8, 2001
Columbia, South Carolina
1. Wal-Mart is currently seeking access across the area that is between the proposed parking lot and
Issaqueena Trail. This area is located within the City of Clemson and is zoned residential. The City of
Clemson initially denied Wal-Mart's request for access. Wal-Mart now has an action pending in circuit
court challenging the City's decision.
2. Further, counsel for CRGC asserted during oral argument that if DHEC issued a state water quality
certification for the Wal-Mart development, CRGC received neither notice nor an opportunity to be
heard on the certification.
3. "Waters of the State" include streams, creeks and all other bodies of surface or underground water
which are within the State. 24 S.C. Code Ann. Regs. 61-9.122.2(b)(93) (Supp. 2000). "Waters of the
United States" include tributaries of waters which may be susceptible to use in interstate or foreign
commerce and all other waters such as intrastate streams which could affect interstate or foreign
commerce. 24 S.C. Code Ann. Regs. 61-9.122.2(b)(94) (Supp. 2000). In this case, the discharge will
be into a tributary of Eighteen Mile Creek.
4. See CRGC's request for contested case hearing filed May 30, 2000; see also ALJD Rule 11 ("The
request for a contested case hearing shall be filed with the affected agency within the time frame
authorized by that agency. The request shall contain the following information: A. . . . the issue(s) for
which the hearing is requested; B. The caption or other information sufficient to identify the decision,
order, action or inaction which is the subject of the hearing; C. The relief requested."); cf. Pringle v.
Builders Transport, 298 S.C. 494, 381 S.E.2d 731 (1989) ("A petition for circuit court review pursuant
to the Administrative Procedures Act (APA) must direct the court's attention to the abuse allegedly
committed below, including a distinct and specific statement of the rulings of which appellant
complains. The circuit court lacks jurisdiction of the appeal if the notice is insufficient.") (citations
omitted).
5. CRGC references another case in which issues concerning consistency with the Coastal Zone
Management Program were considered in a proceeding on a stormwater permit. That case, however, is
distinguishable from the current case, as it involved a project in the state's coastal zone which required
a determination of consistency with the Coastal Zone Management Program as a prerequisite to
issuance of the stormwater permit. See Chapter III, South Carolina Coastal Management Program
Document, page III-62. |